NIPSCO asks commissioners to revisit rejected heavy-haul route, saying it lacks state OK for U.S. 30 bridge
The county attorney told commissioners at a special meeting Tuesday that the Oct. 27 approval of the county's part of NIPSCO's transformer route still stands, while NIPSCO said the state has not cleared the route's Salt Creek bridge on U.S. 30.
PORTER COUNTY, Ind. NIPSCO asked the Porter County Board of Commissioners on Tuesday to take another look at the heavy-haul route the board rejected Nov. 17, after telling the board it still lacks state approval to take its oversize loads across the Salt Creek bridge on U.S. 30, the crossing the first route depends on.
The board called the special meeting for 1 p.m. in Valparaiso with one item on its agenda, the superload permit for NIPSCO's Hobart Station: the road agreement and bond with NIPSCO and the hauler, G&L Corp., for the route the board approved Oct. 27 through Washington, Center and Union townships, all three in Commissioner Barb Regnitz's Center District. As the agenda lists it, that route runs from Montdale Park Drive and County Road 325 East to Division Road, then Smoke Road to U.S. 30, Joliet Road and the Lake County line. NIPSCO told the board the loads are large transformers.
The county's posted video of the meeting ends about 14 minutes in, during a commissioner's remarks and before any motion or vote.
Why the board met again
Commissioner Ed Morales, who led the meeting, opened by saying the board was told at its last meeting that the first route "was no longer good," then learned Friday that the approval of the county's portion still stood. "So that's what brings us back to today," he said.
Asked how many loads the agreement covered, G&L's representative said five. A commissioner then said the board had been told the first route was no longer good because the loads could not use the U.S. 30 bridge over Salt Creek, and asked, "So you still can't?" and was told, "No, sir."
Asked whether the first route had become void with that news, County Attorney Scott McClure told the board that, as things stand, the county's portion of the route is still approved, "even if the route can't be traversed."
Rick Calinski, NIPSCO's director of public affairs and economic development, told the board the company did not ask for the meeting. "We did not submit this request to be on the agenda today or for a special meeting," he said. He said the Indiana Department of Transportation took a second look at the Salt Creek bridge and found it would not be suitable for the haul, which is why NIPSCO brought the second route to the board Nov. 17. He said NIPSCO felt that route was the best and safest choice, and that the company would like a chance to review it with the board and talk about what would make commissioners comfortable with it.
Asked whether the loads could be carried over that bridge another way, Calinski said there had been some conversation about it and handed the question to G&L's representative. The representative said the state usually says no to bridge jumpers, temporary spans set over a bridge, especially on U.S. 30, because both westbound lanes would have to close for the setup and the teardown. When a commissioner said the issue was less whether a span could be used than that the state did not want its road closed, the representative answered, "That is usually the case."
What commissioners said
Commissioner Jim Biggs said every part of the route would be damaged. "There's no single portion of that road, not a single foot of it, that's not going to be damaged," he said, adding that none of the county's nearly 800 roads was built to carry loads like these. He said the county was willing to make a concession because it wants "to be a good neighbor" to Hobart and "a working partner with NIPSCO," but that it needs partners who will work with it, and he called the state's refusal to approve the first route unacceptable. He said a project "this large and this expensive," worth billions of dollars, should have planned how to get its material on site, and he asked when that occurred to NIPSCO or to Amazon and why it was not worked out while approval was being sought for the data center.
"Porter County and its residents get nothing out of this. Nothing," Biggs said. He said he would grant that the work brings union jobs, and that taxpayers want to know why the county would allow its roads to be torn up. "We have to answer that question," he said.
Calinski answered that NIPSCO has worked with G&L many times and has moved hundreds of large transformers with the firm, which carries the insurance and bonds, and that hauls like this one are not out of the norm. He suggested a professional third party inspect the roads before and after the transformers move through, to set a baseline for any repairs. "We don't want to do this at the expense of Porter County residents and the safety and the integrity of the roads," he said. He said that, the way NIPSCO has the project structured, "all of our electric customers will benefit," and that the data center is expected to hire 300 to 400 people.
In the last remarks on the county's video, a commissioner said the board had agreed to the first request believing the state had approved it, and that the Nov. 17 request would have used more county road than the first at the same bond amount. County staff put that route at 7.43 miles of county road against 4.79 miles on the first when the board took it up Nov. 17, and staff said then that the bond NIPSCO's hauler had obtained still met the county's reconstruction requirements.
What came before
The board approved the first route Oct. 27 on a motion by Biggs, seconded by Regnitz, according to the county's minutes, which say multiple residents raised concerns about the route and possible damage to the county's section of it, and that G&L told the board Porter County would hold a $7 million bond. On Nov. 17, county staff said the state had withdrawn permission for a section of U.S. 30, and the board denied, by voice vote, a revised route that would have used Division Road, County Road 200 West, State Road 2 and County Road 150 West to reach U.S. 30.
What comes next
By NIPSCO's account, the loads cannot travel the route approved Oct. 27 until the state clears the Salt Creek crossing, and the company has asked for a chance to go over the route the board turned down Nov. 17 with commissioners again. The board's next regular meeting is at 10 a.m. Tuesday, Dec. 8, in the Commissioners' Chambers of the Administration Center, 155 Indiana Ave., Suite 205, in Valparaiso. Residents can reach the Commissioners' Office at 219-465-3440, weekdays from 8:30 a.m. to 4:30 p.m.
Label: Reported by us.
Corrections
No corrections to this story. If something here is wrong, tell us. Every correction is dated on the story and listed in our public log.
Sources (11)
- Porter County Board of Commissioners special meeting video, Nov. 24, 2026 (Porter County Government)
- Special meeting agenda, Nov. 24, 2026 (Porter County)
- Meeting listing, Porter County calendar (Porter County)
- Board of Commissioners minutes, Oct. 27, 2026 (Porter County)
- Board of Commissioners agenda, Oct. 27, 2026 (Porter County)
- Board of Commissioners meeting video, Nov. 17, 2026 (Porter County Government)
- Board of Commissioners agenda, Nov. 17, 2026 (Porter County)
- Board of Commissioners meeting listing, Dec. 8, 2026, Porter County calendar (Porter County)
- Your Commissioners (Porter County)
- Commissioners' Office directory (Porter County)
- NIPSCO Community Connect newsletter, spring 2026 (NIPSCO)