Four data center plans fell through in Porter County, and no county data center rule has reached a hearing
Where every data center proposal in the county stands, what local rules now say, and what NIPSCO's data center contracts mean for your electric bill starting in 2027.
PORTER COUNTY, Ind. Four large data center campuses proposed in Porter County, from eight buildings in Chesterton to two sites on either side of County Road 450 North near Wheeler, were withdrawn or dropped between June 2024 and September 2025, three of them after residents objected in public. That September, the president of the county commissioners said data centers would be the primary issue for a new Plan Commission subcommittee reviewing the county's zoning rules, and 14 months later no data center rule has come before the Plan Commission, its minutes and agendas show. Meanwhile, Amazon and Microsoft are developing data center campuses in neighboring Jasper and LaPorte counties, and NIPSCO, the northern Indiana electric utility, has signed contracts to power Amazon, Alphabet and Microsoft data centers in the region.
Key numbers
- 4 large data center campuses proposed in Porter County, in Chesterton, Burns Harbor, Valparaiso and Union Township, by PC360's count from local records; all 4 were withdrawn or dropped between June 2024 and September 2025.
- 14 months: the time since Commissioner Jim Biggs said, on Sept. 16, 2025, that data centers had to be "a significant part of the discussion" for a new Plan Commission subcommittee. No data center ordinance has come before the Plan Commission since, according to its posted agendas and minutes.
- 37: the people Valparaiso's March 10, 2025, City Council minutes list as speaking about the data center proposal, by PC360's count. The mayor said the next day that the developer had agreed to withdraw.
- $87 million: the Amazon data center project in Portage that won city tax breaks in December 2023, PC360's sum of the $35 million building and $52 million in equipment the abatements cover.
- 2,400 megawatts: the electric load Amazon has contracted with NIPSCO by the end of 2032, more than the 2,300 megawatts GenCo's president testified NIPSCO forecasts for all of its customers other than data centers in 2028.
- Up to 3,000 megawatts: the new generation NIPSCO's affiliate, GenCo, is building to serve Amazon, which GenCo told regulators Amazon will pay for.
- About $7 a month: the credit a NIPSCO residential customer should see once Amazon reaches full load, NIPSCO testified in the case regulators approved in June.
- $4.50 a month: the residential credit NIPSCO says to expect from January through June 2027 from its three data center contracts, subject to regulatory approval.
- About $49 million: the price NIPSCO said it sold Amazon land for at its Schahfer station in Jasper County, with the net proceeds to go back to its other electric customers as bill credits, subject to regulatory approval.
- 384: the large diesel backup generators in Indiana's draft air permit for an Amazon data center near Wheatfield in Jasper County.
What was proposed in Porter County, and what happened
Chesterton, withdrawn June 2024. Provident Realty Advisors of Dallas proposed eight 150,000-square-foot buildings, a project estimated at $1.3 billion, and withdrew its application in June 2024 after residents raised noise, home values, air, water and energy, The Times of Northwest Indiana reported, according to Inside Indiana Business. The Chesterton Town Council said in a statement, "At its current scale, and especially at this location, the Town Council could never support this project."
Burns Harbor, withdrawn October 2024. Provident also petitioned the Burns Harbor Advisory Plan Commission for a data center campus. On Oct. 7, 2024, the commission approved Provident's request to withdraw that petition by a 7-0 roll call, and its minutes record that the withdrawal "does not prevent someone else from coming before this board" and that the town needed to define data centers in its code. Under town code, a withdrawn petition cannot return to the docket for at least three months. Residents who spoke after the vote urged a 200-day moratorium while the town wrote rules, the minutes show.
Valparaiso, dropped March 2025. On Jan. 9, 2025, the city's Redevelopment Commission unanimously approved an option letting Agincourt Investments LLC study about 180 of the 238 acres the commission owns near St. Mary Medical Center, land bought in 2022 for a regional sports complex that the city dropped in 2023, the city said in a statement it released in early March 2025. Agincourt offered just over $9 million, about $50,000 an acre, against the $20,000 to $22,000 an acre the city paid, and had not asked for a tax abatement or other incentives, the statement said. Agincourt still had to confirm with NIPSCO that enough power could reach the site, work out water with Valparaiso City Utilities while protecting test wells on the land, and win a rezoning from the Plan Commission and City Council.
The City Council's March 10, 2025, meeting ran from 6 p.m. to 10:37 p.m., and its minutes list 37 people who made public comment about their concerns and questions on the data center. The next day, Mayor Jon Costas said in a statement that Agincourt had "agreed to withdraw from pursuing the project, and also to release their option on the land," according to a resident's report in the Redevelopment Commission's March 13, 2025, meeting record, which quotes the statement. In a written response in that same record, the city's Law Department said the commission had understood the concerns of the adjacent neighbors but that "what was not apparent was the broader objection to the concept of a data center in Valparaiso," that "some jumped to conclusions about noise, water consumption, and power usage without knowing any specifics," and that those questions would have been addressed publicly had the process moved forward.
Union Township, dropped by September 2025. AXPK LLC, which the county identified as an affiliate of QTS Data Centers, sought a planned unit development rezoning for two sites the county's map labeled Jeremiah A and Jeremiah B, southwest of Wheeler on either side of County Road 450 North. The Plan Commission held an informational neighborhood meeting on the proposal at the Expo Center on May 13, 2025, where no votes were to be taken. In a written response the county's development department stamped as received July 7, 2025, QTS said no building would be closer than 2,000 feet to Wheeler High School, that it does not use public water to cool its data centers, that the campus would create 125 to 175 operational jobs and more than a thousand construction jobs, and that its "projected annual tax revenue is over $10 million annually once stabilized."
On Aug. 26, 2025, board President Jim Biggs gave the commissioners' data center update. He said the proposal had "prompted hundreds of our residents to share their concerns," that "it has been made public that QTS parent companies has a sizeable financial interest in NIPSCO," and that the board had not received a complete response from NIPSCO or QTS about that relationship. "So, if you want to come here and develop something as large as this data center is proposed to be you had better come to the table with something other than the promise of more tax dollars," he said, the minutes record. At the board's next meeting, on Sept. 16, 2025, Biggs referred to "the decision not to move forward with that project."
The county's data center review
At that Sept. 16 meeting, Biggs told the county's development director, Mike Jabo, that data centers and their locations had to be "a significant part of the discussion" for a new Plan Commission subcommittee being formed to review the county's Unified Development Ordinance, the zoning code the county adopted in 2007. Jabo said he had talked with New Albany, Ohio, and St. Joseph County about their approaches and noted that Lake County had just passed ordinances.
A resident speaking for a group opposed to data centers in Duneland, Valparaiso and Union Township asked the board for a stricter ordinance and a temporary moratorium of 200 to 250 days on new data center applications. Biggs answered that the board had to be careful. "We don't want to create ordinances here or moratoriums that end up being to our disadvantage," he said. "Data centers are coming. Now whether or not they'll be located in this county is yet to be seen. But there is an economic advantage of having them here." He told her the subcommittee would take up data centers as "the primary issue that we're going to take a look at," and added, "We don't want massive heavy industrial sprawl taking over the bottom third of our county or the side thirds," the minutes record.
On Oct. 7, 2025, the commissioners opened applications for up to three citizen seats on the subcommittee, each for a 24-month term. Jabo told the board that "at the last meeting you asked us to look at data centers and other big operations," adding, "That is not the only reason we are meeting." He said the group was also working through the broader ordinance update and called it "a long-term thing," though "we are going to be putting stuff out as we work. It will be a continually working rolling process," the minutes show.
In May 2026, Jabo told the Plan Commission the subcommittee had been discussing building heights, planned unit developments, shipping containers and subdivisions. No data center ordinance has come before the commission in 2026, according to its posted agendas and minutes. Three of its 2026 meetings, in June, August and October, were canceled for lack of business. Its Nov. 19 meeting, a public hearing on the county's zoning rules under the state's 2026 housing law, House Enrolled Act 1001, had no data center item on the agenda, and the commission took no action that night. Jabo told the commission at that hearing that a full update of the Unified Development Ordinance, folding in the amendments approved since 2007, will come to it in January and go to the commissioners in January and February, and that his department had rewritten the ordinance's chapter on planned unit developments, the kind of rezoning QTS sought in Union Township, and is sending that draft out for review.
At the commissioners' March 31, 2026, meeting, Commissioner Edward Morales said there had been rumors of a possible proposed data center and that they were not true, the meeting minutes record.
The one that won approval: Amazon in Portage
On Dec. 5, 2023, the Portage City Council finalized two property tax abatements for an Amazon data center near the AmeriPlex development, Lakeshore Public Media reported. One phases in taxes over 10 years on a $35 million building and the other over five years on $52 million in computer equipment. The data center would start with 10 employees each earning at least $100,000 a year and was expected to produce $7.5 million in tax revenue over 10 years, compared with $180,000 if the land stayed undeveloped, Portage Economic Development Corp. Executive Director Andy Maletta said at the time. Council Member Ferdinand Alvarez voted against the abatements, saying a company of Amazon's standing could afford its own property taxes, the station reported.
Who decides, and the rules now in place
In unincorporated Porter County, a data center needs a rezoning. Under the county's planned unit development process, the Plan Commission holds a public hearing and sends the commissioners a favorable, unfavorable or no recommendation, and the commissioners hold their own hearing at a first meeting and may adopt, reject or amend the ordinance at a second, the county's development department explained at the May 2025 meeting. Notice of the Plan Commission hearing goes to all surrounding property owners and runs in the local newspaper, and a rejected or amended ordinance goes back to the Plan Commission, according to the same presentation. The County Council's role is limited to money matters such as abatements and bonds, the council said in a 2025 statement.
Valparaiso adopted a moratorium on new data centers on Aug. 10, 2026, by a 6-0 vote with Council Member Diana Reed absent, the council's minutes show. The Plan Commission had recommended it 5-1 after an Aug. 4 public hearing. In July the council voted 6-1 to strike a July 31, 2028, end date from the draft, after the city attorney, speaking through Mayor Costas, cautioned that a moratorium with no end date would work as a ban, which carries different legal implications, and Costas recommended keeping the two-year term. The pause now lasts until rules for data centers take effect in the city's Unified Development Ordinance, unless the council repeals or extends it. As drafted, the ordinance does not apply to existing lawful uses, routine maintenance, repair or renovation of existing facilities, or projects with vested rights under Indiana law, and the July amendment changed only its end date.
Planning Director Bob Thompson told the council the rewrite of the Unified Development Ordinance would take about 18 months from late August or early September. In May the council asked the Plan Commission to write data center rules, using as a guide a draft from the city's Environmental Advisory Board that would allow data centers only in heavy industrial zoning, on at least 100 acres, with a 55-decibel noise limit, a decommissioning plan and proof that electric service would not hurt existing ratepayers. On Oct. 6 the Plan Commission heard from INFRA, a consulting team the Plan Commission is engaging to help evaluate and develop the standards, and the INFRA team said its role is advisory, with legal counsel responsible for drafting, the minutes show. Council Member Ellen Kapitan, who brought the draft, said in May that no data center project had been proposed for Valparaiso.
In Portage, Mayor Austin Bonta told the council July 7 that the Plan Commission had unanimously recommended a Technology Campus zoning ordinance creating a new classification for data centers, removing them from districts where they had been allowed as warehouses, the minutes show. At that meeting one resident urged the city to prohibit new data centers, while Plan Commission member Jeremiah Montgomery said the ordinance sets standards rather than approving any project. Asked by Porter County 360 about that remark, Montgomery answered in an email on Nov. 17 that adopting the ordinance "was not an approval of any particular data center project" but "established a regulatory framework and development standards" for weighing such proposals, covering setbacks, buffering, landscaping, lighting, noise and cooling systems. "Any future proposal should be evaluated on its own merits, with careful consideration given to its potential impacts on the surrounding community," he wrote. The council adopted the ordinance, No. 26-09, on Aug. 4, 2026, Inside Indiana Business reported. As adopted, it makes the Technology Campus district the only one where a data center can go, requires a 500-foot setback from residential districts, caps noise at 55 decibels and buildings at 65 feet, and treats any project of more than 50 megawatts or 500,000 square feet as hyperscale, which also needs a planned development approval.
Power: NIPSCO, GenCo and the contracts
NIPSCO formed an affiliate, NIPSCO Generation LLC, known as GenCo and now called NiSource Generation Company in NiSource's releases, to build power plants for very large customers, and the Indiana Utility Regulatory Commission approved that structure on Sept. 24, 2025, in Cause No. 46183. Its main purpose, NIPSCO President Vince Parisi testified, is to protect NIPSCO's other customers from the risks of the large investments needed to serve those customers.
On June 17, 2026, the commission approved NIPSCO's 15-year contract with Amazon Data Services in Cause No. 46322. Service begins Jan. 1, 2027, and rises to as much as 2,400 megawatts by the end of 2032. GenCo is building up to 3,000 megawatts of generation to serve it, including two 1,300-megawatt natural gas plants at the Schahfer Generation Station in Jasper County and a 400-megawatt battery system at the former Mitchell Generation Station in Lake County, and GenCo's president testified that Amazon will pay all of those costs, according to the commission's companion order in Cause No. 46362. Amazon will also fully fund the added transmission needed to serve it, the commission wrote in the contract order. For scale, GenCo's president testified that NIPSCO's load from all customers other than data centers is forecast at 2,300 megawatts in 2028.
The data center locations in the Amazon contract are listed in a confidential exhibit. The public order says one of them is on property where NIPSCO already operates, that NIPSCO would supply that data center's cooling water and handle its wastewater, and that NIPSCO would sell Amazon the land at appraised market value, with any gain passed back to its other customers. The settlement terms the commission approved refer to "the Schahfer land sale to Amazon," at NIPSCO's Jasper County station.
That reference "relates to a land transaction," Jessica Cantarelli, communications manager for Northern Indiana Public Service Co., said in an email to Porter County 360 on Nov. 23. NIPSCO sold Amazon land at Schahfer, where she said Amazon will build a data center, for about $49 million, and the net proceeds are being passed back to NIPSCO's other electric customers as bill credits beginning in January 2027, subject to the commission's approval, she said. Amazon has publicly announced data center locations in Hobart, in Lake County, and Wheatfield, in Jasper County, she said, adding, "We have not publicly identified any data center served under our agreements with Amazon, Alphabet or Microsoft as being located in Porter County." Asked whether NIPSCO is reviewing any request for large-load electric service at a Porter County site, she wrote, "We have not announced a data center project in Porter County. As a matter of practice, we do not comment on potential customers or projects unless and until they are publicly announced."
NiSource, NIPSCO's parent, has also signed a contract with a subsidiary of Alphabet, Google's parent, for a northern Indiana data center it did not name. NiSource said in April that it expected service to begin in summer 2026, and electric service to that data center began in summer 2026, "consistent with the timeline we announced in April," Cantarelli said. NiSource also signed a 20-year contract with Microsoft, beginning in 2028, for what NiSource called Microsoft's previously announced northwest Indiana campus, for which GenCo is adding about 1,100 megawatts of generation. Microsoft's own planning boards for its roughly 500-acre site in La Porte show construction of the first data center building complete in early spring 2029, a date the boards note does not mark when it will operate.
What it could mean for your bill
Amazon will pay NIPSCO charges for its use of the existing electric system, and an estimated $1.1 billion of that will be passed back to NIPSCO's other customers as a separate credit on their bills, the commission wrote. Once Amazon reaches full load, a residential customer should see a credit of about $7 a month, or $82 a year, Parisi testified, and the credit grows if Amazon uses more power than estimated. NiSource now puts expected savings from its Amazon, Alphabet and Microsoft contracts at about $1.75 billion, "as much as $140 per customer annually." NIPSCO's current estimate is $1.75 billion over the next 20 years, spread across about 500,000 electric customers and not specific to Porter County, Cantarelli said, and residential customers are expected to receive up to that $140 a year "as the projects ramp up," starting at $4.50 a month in January 2027, assuming the commission approves in time.
The Amazon settlement also sets up a Customer Fund paid entirely by NIPSCO and GenCo shareholders, an estimated $15 million over the contract's term, the commission wrote. Half goes to local communities in NIPSCO's territory where the data center and generation investments are made, and the other half is credited to all NIPSCO electric customers.
Citizens Action Coalition of Indiana argued that a greater share of the Amazon credit should go to residential customers because of affordability, and the commission declined, approving the allocation in the settlement among NIPSCO, the Indiana Office of Utility Consumer Counselor and the NIPSCO Industrial Group as "a reasonable compromise." LaPorte County's commissioners agreed not to oppose the settlement in an addendum in which NIPSCO and GenCo committed to a priority evaluation of LaPorte County sites for future generation, with special emphasis on industrially zoned land such as the Kingsbury Industrial Park, if more data center demand calls for it.
In the commission staff's survey of July 1 bills, a NIPSCO home using 1,000 kilowatt-hours a month paid $225.91 before taxes, the most of the eight regulated utilities surveyed, $1.01 more than CenterPoint Energy Indiana South and down 3.3% from $233.62 a year earlier.
Taxes and incentives
Indiana exempts qualified data centers from sales tax on their equipment and energy for up to 25 years, or up to 50 years when the investment tops $750 million, under a program the Indiana Economic Development Corp. awards, and local governments may also exempt the computer equipment from property tax when a data center invests at least $25 million. House Enrolled Act 1210, signed March 12, 2026, requires certain qualified data centers to reach an agreement with local officials before using a state exemption certificate, and those agreements can send the county or city up to 1% of the exempted sales tax on the data center's electricity, starting in the 2027 fiscal year, according to the Legislative Services Agency's fiscal note.
Water, noise and backup power
How much water a data center draws depends on its cooling design, and QTS told Porter County its closed-loop cooling does not use public water, though the project required public water and sewer upgrades it said it would fund. Agincourt would have had to work out its water with Valparaiso City Utilities, the city said. At the one contract site the Amazon order describes, on NIPSCO property, NIPSCO would supply mainly industrial water for cooling.
The Indiana Department of Environmental Management's draft air permit for Amazon's data center on County Road 1350 North near Wheatfield lists 384 diesel emergency generators rated at 2,750 kilowatts each, each fitted with selective catalytic reduction, a particulate filter and its own 6,500-gallon fuel tank, plus seven smaller emergency generators and 14 bulk fuel tanks of 12,000 gallons. By PC360's math, those 384 units add up to 1,056 megawatts of backup capacity. IDEM scheduled a virtual public hearing for Nov. 10, and public comment on the draft permit ran through Nov. 16.
What residents have asked
At the May 2025 Union Township neighborhood meeting, residents' questions, as QTS listed them in its written answers, covered how close buildings would sit to the schools, construction traffic and work hours, operating noise, water supply and drainage, diesel generators and fuel tanks, electromagnetic fields, light, property values, and what the county would gain in jobs and taxes. Before the county commissioners in September 2025, a resident speaking for an opposition group asked for a moratorium and for large data centers to be classed as a heavy industrial use. In Valparaiso, a council member said at the March 10, 2025, meeting that residents felt the process lacked transparency. In Portage, the debate in July was whether to regulate data centers or prohibit them.
Porter County 360 asked Commissioners Jim Biggs and Edward Morales, county development director Mike Jabo, QTS, Amazon, Google, Microsoft, the office of Valparaiso Mayor Jon Costas, Valparaiso Planning Director Bob Thompson, the Portage mayor's office, Portage Council Member Ferdinand Alvarez and Portage Economic Development Corp. Executive Director Andy Maletta about this story on Nov. 17, and Valparaiso Council Member Ellen Kapitan on Nov. 15, and none of them had answered by Wednesday afternoon, Nov. 25, while NIPSCO and Montgomery answered, as reported above; other answers will be added when they come in.
What is still open
- Whether the county's Plan Commission subcommittee will bring data center standards to a public hearing, and when.
- The date QTS's Union Township petition was formally withdrawn.
- Where the Amazon contract's other confidential data center sites are; NIPSCO says it has not publicly identified any data center it serves under its three agreements as being in Porter County and does not comment on projects before they are announced.
- When Valparaiso's data center standards will reach a public hearing.
- Whether Amazon's Portage data center is running and whether it has met its job and investment figures.
What's next
- Jan. 1, 2027: NIPSCO's service to Amazon begins under the approved contract, rising through 2032.
- January 2027: the county's updated Unified Development Ordinance is due before the Plan Commission, then the commissioners in January and February, Jabo said Nov. 19.
- January 2027: NIPSCO expects residential bill credits from its three data center contracts to begin at $4.50 a month through June, subject to the commission's approval.
- 2027 and into 2028: Valparaiso's ordinance rewrite, which Thompson put at about 18 months; the moratorium stays in place until data center rules take effect.
- 2028: Microsoft's NIPSCO service is scheduled to begin.
Label: Reported by us.
Corrections
No corrections to this story. If something here is wrong, tell us. Every correction is dated on the story and listed in our public log.
Sources (25)
- Board of Commissioners minutes, Aug. 26, Sept. 16 and Oct. 7, 2025, and March 31, 2026, Porter CountyAlso portercountyin.gov/AgendaCenter/ViewFile/Minutes/_09162025-2049, portercountyin.gov/AgendaCenter/ViewFile/Minutes/_10072025-2066, portercountyin.gov/AgendaCenter/ViewFile/Minutes/_03312026-2144
- Plan Commission minutes, Aug. 27, Sept. 24, Oct. 22 and Dec. 10, 2025, and Feb. 25, March 25, April 22, May 27 and July 22, 2026; agendas and notices, Jan. 28, June 24, Aug. 26, Sept. 23, Oct. 28 and Nov. 19, 2026, Porter CountyAlso portercountyin.gov/AgendaCenter/ViewFile/Minutes/_09242025-2053, portercountyin.gov/AgendaCenter/ViewFile/Minutes/_10222025-2069, portercountyin.gov/AgendaCenter/ViewFile/Minutes/_12102025-2088, portercountyin.gov/AgendaCenter/ViewFile/Minutes/_02252026-2122, portercountyin.gov/AgendaCenter/ViewFile/Minutes/_03252026-2134, portercountyin.gov/AgendaCenter/ViewFile/Minutes/_04222026-2148, portercountyin.gov/AgendaCenter/ViewFile/Minutes/_05272026-2166, portercountyin.gov/AgendaCenter/ViewFile/Minutes/_07222026-2194, portercountyin.gov/AgendaCenter/ViewFile/Agenda/_01282026-2109, portercountyin.gov/AgendaCenter/ViewFile/Agenda/_06242026-2178, portercountyin.gov/AgendaCenter/ViewFile/Agenda/_08262026-2209, portercountyin.gov/AgendaCenter/ViewFile/Agenda/_09232026-2225, portercountyin.gov/AgendaCenter/ViewFile/Agenda/_10282026-2247, portercountyin.gov/AgendaCenter/ViewFile/Agenda/_11192026-2257
- Plan Commission, Nov. 19, 2026, meeting recording, Porter County Government
- Union Township Data Center page, notices, May 13, 2025, neighborhood meeting notice and presentation, and QTS response received July 7, 2025, Porter County Department of Development and Storm Water ManagementAlso portercountyin.gov/2147/Documents
- Porter County Council Statement on Data Centers, Porter County
- City Council minutes, March 10, 2025, and May 11, July 13 and Aug. 10, 2026, Redevelopment Commission meeting record, March 13, 2025, and Plan Commission minutes, Oct. 6, 2026, City of ValparaisoAlso ci.valparaiso.in.us/AgendaCenter/ViewFile/Minutes/_05112026-1718, ci.valparaiso.in.us/AgendaCenter/ViewFile/Minutes/_07132026-1743, ci.valparaiso.in.us/AgendaCenter/ViewFile/Minutes/_08102026-1756, ci.valparaiso.in.us/AgendaCenter/ViewFile/Minutes/_03132025-1547, ci.valparaiso.in.us/AgendaCenter/ViewFile/Minutes/_10062026-1773
- Draft Ordinance No. 16-2026, An Ordinance Establishing a Temporary Moratorium on New Data Center Development, City of Valparaiso, July 2026
- City of Valparaiso statement on a potential data center, March 2025, full text as published by WIMS, March 8, 2025
- Common Council agenda, Aug. 4, 2026, and minutes, July 7, 2026, City of PortageAlso portagein.gov/AgendaCenter/ViewFile/Minutes/_07072026-352
- Advisory Plan Commission minutes, Oct. 7, 2024, Town of Burns Harbor
- Order in Cause No. 46322 (NIPSCO and GenCo, Amazon Data Services special contract), Indiana Utility Regulatory Commission, June 17, 2026
- Order in Cause No. 46362 (GenCo generation resources), Indiana Utility Regulatory Commission, June 17, 2026
- 2026 Residential Bill Survey, July 1, 2026 billing, update of July 28, 2026, Indiana Utility Regulatory Commission
- NiSource announces long-term agreement with Microsoft, NIPSCO, Oct. 16, 2026
- NiSource announces strategic energy infrastructure agreements, NiSource, April 16, 2026
- Email from Jessica Cantarelli, communications manager, Northern Indiana Public Service Co., to Porter County 360, Nov. 23, 2026, answering PC360's questions of Nov. 17; email, no web copy
- Email from Jeremiah Montgomery, Portage Plan Commission member, to Porter County 360, Nov. 17, 2026, answering PC360's question of Nov. 17; email, no web copy
- La Porte datacenter community boards, Microsoft, April 2026
- Notice of extension of public comment period and draft permit T 073-50413-00077, Amazon Data Services, Inc., Jasper County, Indiana Department of Environmental Management, 2026Also permits.air.idem.in.gov/50413d.pdf
- Data Center Sales Tax Exemption, Indiana Economic Development Corp.
- Fiscal impact statement, HB 1210, 2026 session, Legislative Services Agency, March 3, 2026 (copy atAlso in.gov/dlgf/files/2026-memos/260429-Cockerill-Memo-Legislation-Affecting-Assessment-Matters.pdf
- "Plug pulled on $1.3 billion Chesterton data center proposal in face of opposition," The Times of Northwest Indiana, June 11, 2024
- "Chesterton data center project withdrawn," Inside Indiana Business, June 12, 2024, reporting from The Times of Northwest Indiana
- "Portage Council approves tax abatements for Amazon data center," Lakeshore Public Media, Dec. 7, 2023
- "Portage council approves ordinance establishing data center restrictions," Inside Indiana Business, Aug. 4, 2026