Reported by us | Valparaiso

Valparaiso Board of Works approves $374,068 for 2027 Franklin Street paving and a $99,860 sidewalk contract

The board also approved an inspection agreement of up to $403,220.93 for the Barrel District Trail, two crosswalks and a Rebecca Street parking limit, and pushed six code cases to March.

By Chuck Vieira and the PC360 Government Desk | Published Nov. 26, 2026 | Last verified Nov. 26, 2026, 7:01 a.m. CT

Valparaiso will spend $374,068.05 from its paving funds on the road portion of next year's Franklin Street water main and storm sewer replacement, after the Board of Public Works and Safety approved the money Wednesday.

The paving covers Franklin Street from Institute Street to Bush Street, Deputy Engineer Dylan Harakal told the board. He said the street has a PASER pavement rating of 2 and is on the city's paving list for 2027. The city had budgeted $500,000 for the road work in its 2027 capital improvements plan, he said, so the approved amount comes in about $125,900 under that figure.

Harakal said the paving will be part of the water main and storm sewer project, which the city utilities board recommended at its Tuesday meeting. Milestone Contractors, which the city has used on other projects, will do the road work under the prime contractor, he said, and the job is expected to be finished by July. Asked by a board member which pot of money the $374,068.05 comes from, city staff said the paving money is not split by source and the amount comes out of the city's combined paving funds.

City engineering and utilities staff first put the whole Franklin Street job at about $1.9 million in October: about $700,000 for water main, $700,000 for storm sewer and $500,000 for the roadway, according to the board's Oct. 23 minutes. At Monday's City Council meeting, Council member Ryan Moore, the council's utilities liaison, said the city utilities board had opened three bids for the project, ranging from $1.6 million to $1.7 million, below that October estimate.

All three board members, Mayor Jon Costas, City Administrator Steve Poulos and Katrina Spence-Smock, attended the 11 a.m. meeting at City Hall. Each item passed on a voice vote, and no member was heard voting no.

Sidewalks on Don Hovey Drive and Axe Avenue

The board awarded a $99,860 contract to Davis Concrete for sidewalk work on Don Hovey Drive and Axe Avenue, which Engineering Director Max Rehlander described as places where sidewalk is either missing or in very poor condition. He said staff asked six firms for prices and three answered: Davis Concrete at $99,860, Milestone Contractors at $104,550 and a third firm at $225,195.

The work will be paid from the city's local income tax sidewalk fund, Rehlander said, and the 2026 sidewalk capital improvement plan had a contingency of about $146,000, so money is available.

Barrel District Trail inspection

The board approved a construction inspection agreement with American Structure Point for the Barrel District Trail, a multi-use trail from the area around the city's transit-oriented development north to downtown, for no more than $403,220.93. At its Nov. 13 meeting, the board awarded the trail's $3.9 million construction contract to Gariup Construction.

Rehlander said three firms sent letters of interest and one later declined to submit, and a city selection committee ranked American Structure Point highest. The Indiana Department of Transportation approved the agreement Monday, he said. Federal highway funds pay 80% and local funds 20%, with the Valparaiso Redevelopment Commission covering the local share of up to $80,644.19.

Crosswalks and parking

The board approved three recommendations from the city's Traffic and Safety Committee, which met Nov. 16:

The committee's Nov. 16 agenda had also listed a request for a stop sign at Locust and Chicago streets. It was not among the recommendations brought to the board.

Other business

The board approved a 12.2-acre replat of Lot 1 in the Airport Business and Industrial Park at the east end of Bowman Drive, splitting it into lots of 5.4 and 6.8 acres. Planning and Transit Director Bob Thompson said no public infrastructure needs to be extended; the new lot will be reached by an access easement off the cul-de-sac.

The board also approved a $2,700 agreement with Marauder Security for an outside penetration test of the city's computer network over a couple of days, which the firm will not announce ahead of time, as well as street closures for the Extra Mile Resolution Run on Jan. 1 and the Extra Mile Valentine's Day Run on Feb. 7. It accepted a conflict of interest disclosure statement and approved the city's 2027 holiday schedule.

Six property maintenance cases, at 1106 Institute St., 4102 Campbell, 416 Center St., 352 Locust St., 702 Garfield Ave. and 103 Morgan Blvd., were continued to the board's March 25, 2027, meeting. Code enforcement staff said the owners had promised to finish the work and were given another 30 days, but none of the properties had come into compliance since the board's last meeting. The cases go to March because the city does not usually make owners clean up their properties during the snowy months, staff said.

No members of the public were there to speak during public comment, and the meeting ran about 14 minutes.

What's next

The board's next meeting is scheduled for 11 a.m. Friday, Dec. 11, at City Hall, 166 Lincolnway. Residents who cannot attend can email comments or questions on agenda items before the meeting to mpalmer@valpo.us, and the meetings stream live and are posted on the city's Watch City Meetings page.

Label: Reported by us.

Corrections

No corrections to this story. If something here is wrong, tell us. Every correction is dated on the story and listed in our public log.

Sources (7)

  1. Board of Public Works and Safety meeting video, Nov. 25, 2026, City of Valparaiso
  2. Board of Public Works and Safety agenda, Nov. 25, 2026
  3. Board of Public Works and Safety minutes, Oct. 23, 2026
  4. City Council meeting video, Nov. 23, 2026, City of Valparaiso
  5. Porter County 360, "Valparaiso awards $3.9 million downtown trail contract and approves firefighters' union contract," Nov. 13, 2026
  6. Traffic and Safety Committee minutes, Oct. 19, 2026
  7. Porter County 360, Traffic and Safety Committee preview, Nov. 13, 2026

This story on the full site